New Hampton
Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).
Described as new. The quoted wording calls this substation new. “Construct a new 230/115kV substation next to the existing Hampton 115kV substation.” — TEAMS 21567, plan p.166
The project title, "GTC: NEW HAMPTON 230/115kV SUB", names the station; the description builds one new substation beside the existing Hampton station, so the new one is not Hampton.
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: NEW HAMPTON 230/115kV SUB Construct a new 230/115kV substation next to the existing Hampton 115kV substation. TEAMS 21567 · plan p.166 · zone 208 |
GTC | In the plan p.13 |
Jun 1, 2028 | New project | Hampton, New Hampton |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.