Hillje

Named in 10 listed projects in ERCOT’s transmission project tracking workbook, in Wharton County. First named in the release with data as of October 1, 2020.

Whartoncounty as printed
345, 765kV
AEP TCC, CNPutility
10projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand Hillje 345kV substation” — project 72059, as the utility reported it

Also printed as: HILLJE

A HIFLD substation record has the same name and county: HILLJE (WHARTON County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Loop Ckt.72H into Morley substation to create new Ckt.72 Hillje to Morley to Julia.
ERCOT project 103797A · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
345 Dec 2031 MORLEY to HILLJE/JULIA
Wharton County
MORLEY, HILLJE, JULIA
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Loop Ckt.64E into Morley substation to create new Ckt.64 Hillje to Morley to Wolf.
ERCOT project 103797B · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
345 Dec 2031 MORLEY to HILLJE/WOLF
Wharton County
MORLEY, HILLJE, WOLF
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 765kV CEHE substation. Install 765/345kV Autotransformer A3 with connection to Morley 345kV substation.
ERCOT project 103797E · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
765 Dec 2031 MORLEY to HILLJE/WOLF
Wharton County
MORLEY, HILLJE, WOLF
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Install 345kV Ckt.1 Hillje to Morley. Install 345kV Ckt.2 Hillje to Morley.
ERCOT project 103797F · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
345 Dec 2031 MORLEY to HILLJE/JULIA
Wharton County
MORLEY, HILLJE, JULIA
Blu Lacy to Hillje: Construct New 765 kV Line
Construct a new 765 kV single circuit line from Blu Lacy to Howard
ERCOT project 103809 · utility no. TP2025322 · RPG 25RPG025
AEP TCC
Tier 1
Planned
Future tab
765 Jan 2032 Blu Lacy to Hillje
Nueces / Wharton County
Blu Lacy, Hillje
This models the new CEHE Raider Substation and upgrades required for a proposed load addition
Loop 345 kV Ckt. 64 Wolf-Hillje line into the new 345 kV CEHE Raider substation. Upgrade line relaying on Ckt 64 WOLF-Raider-Hillje.
ERCOT project 110068B
CNP
Tier 4
Planned
Future tab
345 May 2029 Raider to Wolf/Hillje
Wharton County
Raider, Wolf, Hillje
Hillje 345kV Substation Expansion for Ramsey Storage - Generator Interconnection to FLATLA (FLA) (21INR0505)
Expand Hillje 345kV substation and install one generator lead for new interconnection to FLATLA (FLA) customer substation for Ramsey Storage
ERCOT project 72059
CNP
Tier 4
Planned
Future tab
345 Dec 2027 Hillje
Wharton County
Hillje
Hillje 345kV Substation Expansion for Space City Solar - Generator Interconnection (21INR0341)
Expand Hillje 345kV substation and install one generator lead for new interconnection to MIDANE customer substation for Space City Solar
ERCOT project 78495
CNP
Tier 4
Planned
Future tab
345 Dec 2027 Hillje to MIDANE
Wharton County
Hillje, MIDANE
Facility Ratings Methodology Phase 2 (FRM2) Upgrades
Upgrade STP equipment on Ckt.44 STP to Hillje to increase thermal limits as part of FRM2 upgrades.
ERCOT project 99453W
CNP
Tier 4
Planned
Current-year planned tab
345 Dec 2026 STP to Hillje
Matagorda / Wharton County
STP, Hillje
Facility Ratings Methodology Phase 2 (FRM2) Upgrades
Upgrade Hillje equipment on Ckt.44 STP to Hillje to increase thermal limits as part of FRM2 upgrades.
ERCOT project 99453X
CNP
Tier 4
Planned
Current-year planned tab
345 Dec 2026 STP to Hillje
Matagorda / Wharton County
STP, Hillje

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026103809Projected in-service dateNov 2031 → Jan 2032
October 1, 2026110068BStatus as reportedConceptual → Planned
October 1, 2026110068BProjected in-service dateOct 2028 → May 2029
July 13, 2026110068BFirst listedon the Future tab
July 13, 202699453XProjected in-service dateMay 2026 → Dec 2026
June 1, 2026103797AFirst listedon the Future tab
June 1, 2026103797BFirst listedon the Future tab
June 1, 2026103797EFirst listedon the Future tab
June 1, 2026103797FFirst listedon the Future tab
June 1, 2026103809First listedon the Future tab
June 1, 202699453WProjected in-service dateMay 2026 → Dec 2026
February 1, 202699453WMoved between tabsFuture → Current-year planned
February 1, 202699453XMoved between tabsFuture → Current-year planned
February 1, 202699453XProjected in-service dateOct 2029 → May 2026
October 1, 202578495Moved between tabsCurrent-year planned → Future
October 1, 202578495Projected in-service dateMay 2025 → Dec 2027
October 1, 202599453WFirst listedon the Future tab
October 1, 202599453XFirst listedon the Future tab
June 1, 202572059Projected in-service dateOct 2025 → Dec 2027
June 1, 202578495Moved between tabsFuture → Current-year planned
June 1, 202472059Projected in-service dateMay 2024 → Oct 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.