Hillje
Named in 10 listed projects in ERCOT’s transmission project tracking workbook, in Wharton County. First named in the release with data as of October 1, 2020.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand Hillje 345kV substation” — project 72059, as the utility reported it
Also printed as: HILLJE
A HIFLD substation record has the same name and county: HILLJE (WHARTON County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| This models CEHE's Portion of the 765 kV STEP project Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Loop Ckt.72H into Morley substation to create new Ckt.72 Hillje to Morley to Julia. ERCOT project 103797A · RPG 25RPG025 |
CNP Tier 1 |
Planned Future tab |
345 | Dec 2031 | MORLEY to HILLJE/JULIA Wharton County |
MORLEY, HILLJE, JULIA |
| This models CEHE's Portion of the 765 kV STEP project Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Loop Ckt.64E into Morley substation to create new Ckt.64 Hillje to Morley to Wolf. ERCOT project 103797B · RPG 25RPG025 |
CNP Tier 1 |
Planned Future tab |
345 | Dec 2031 | MORLEY to HILLJE/WOLF Wharton County |
MORLEY, HILLJE, WOLF |
| This models CEHE's Portion of the 765 kV STEP project Install new Morley (MLY) 765kV CEHE substation. Install 765/345kV Autotransformer A3 with connection to Morley 345kV substation. ERCOT project 103797E · RPG 25RPG025 |
CNP Tier 1 |
Planned Future tab |
765 | Dec 2031 | MORLEY to HILLJE/WOLF Wharton County |
MORLEY, HILLJE, WOLF |
| This models CEHE's Portion of the 765 kV STEP project Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Install 345kV Ckt.1 Hillje to Morley. Install 345kV Ckt.2 Hillje to Morley. ERCOT project 103797F · RPG 25RPG025 |
CNP Tier 1 |
Planned Future tab |
345 | Dec 2031 | MORLEY to HILLJE/JULIA Wharton County |
MORLEY, HILLJE, JULIA |
| Blu Lacy to Hillje: Construct New 765 kV Line Construct a new 765 kV single circuit line from Blu Lacy to Howard ERCOT project 103809 · utility no. TP2025322 · RPG 25RPG025 |
AEP TCC Tier 1 |
Planned Future tab |
765 | Jan 2032 | Blu Lacy to Hillje Nueces / Wharton County |
Blu Lacy, Hillje |
| This models the new CEHE Raider Substation and upgrades required for a proposed load addition Loop 345 kV Ckt. 64 Wolf-Hillje line into the new 345 kV CEHE Raider substation. Upgrade line relaying on Ckt 64 WOLF-Raider-Hillje. ERCOT project 110068B |
CNP Tier 4 |
Planned Future tab |
345 | May 2029 | Raider to Wolf/Hillje Wharton County |
Raider, Wolf, Hillje |
| Hillje 345kV Substation Expansion for Ramsey Storage - Generator Interconnection to FLATLA (FLA) (21INR0505) Expand Hillje 345kV substation and install one generator lead for new interconnection to FLATLA (FLA) customer substation for Ramsey Storage ERCOT project 72059 |
CNP Tier 4 |
Planned Future tab |
345 | Dec 2027 | Hillje Wharton County |
Hillje |
| Hillje 345kV Substation Expansion for Space City Solar - Generator Interconnection (21INR0341) Expand Hillje 345kV substation and install one generator lead for new interconnection to MIDANE customer substation for Space City Solar ERCOT project 78495 |
CNP Tier 4 |
Planned Future tab |
345 | Dec 2027 | Hillje to MIDANE Wharton County |
Hillje, MIDANE |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade STP equipment on Ckt.44 STP to Hillje to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453W |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Dec 2026 | STP to Hillje Matagorda / Wharton County |
STP, Hillje |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade Hillje equipment on Ckt.44 STP to Hillje to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453X |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Dec 2026 | STP to Hillje Matagorda / Wharton County |
STP, Hillje |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 103809 | Projected in-service date | Nov 2031 → Jan 2032 |
| October 1, 2026 | 110068B | Status as reported | Conceptual → Planned |
| October 1, 2026 | 110068B | Projected in-service date | Oct 2028 → May 2029 |
| July 13, 2026 | 110068B | First listed | on the Future tab |
| July 13, 2026 | 99453X | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2026 | 103797A | First listed | on the Future tab |
| June 1, 2026 | 103797B | First listed | on the Future tab |
| June 1, 2026 | 103797E | First listed | on the Future tab |
| June 1, 2026 | 103797F | First listed | on the Future tab |
| June 1, 2026 | 103809 | First listed | on the Future tab |
| June 1, 2026 | 99453W | Projected in-service date | May 2026 → Dec 2026 |
| February 1, 2026 | 99453W | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99453X | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99453X | Projected in-service date | Oct 2029 → May 2026 |
| October 1, 2025 | 78495 | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 78495 | Projected in-service date | May 2025 → Dec 2027 |
| October 1, 2025 | 99453W | First listed | on the Future tab |
| October 1, 2025 | 99453X | First listed | on the Future tab |
| June 1, 2025 | 72059 | Projected in-service date | Oct 2025 → Dec 2027 |
| June 1, 2025 | 78495 | Moved between tabs | Future → Current-year planned |
| June 1, 2024 | 72059 | Projected in-service date | May 2024 → Oct 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.