MORLEY

Named in 10 listed projects in ERCOT’s transmission project tracking workbook, in Wharton County. First named in the release with data as of June 1, 2026.

Whartoncounty as printed
345, 765kV
CNPutility
10projects listed

Also printed as: Morley

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Loop Ckt.72H into Morley substation to create new Ckt.72 Hillje to Morley to Julia.
ERCOT project 103797A · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
345 Dec 2031 MORLEY to HILLJE/JULIA
Wharton County
MORLEY, HILLJE, JULIA
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Loop Ckt.64E into Morley substation to create new Ckt.64 Hillje to Morley to Wolf.
ERCOT project 103797B · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
345 Dec 2031 MORLEY to HILLJE/WOLF
Wharton County
MORLEY, HILLJE, WOLF
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 765kV CEHE substation. Install 765/345kV Autotransformer A1 with connection to Morley 345kV substation.
ERCOT project 103797C · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
765 Dec 2031 MORLEY
Wharton County
MORLEY
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 765kV CEHE substation. Install 765/345kV Autotransformer A2 with connection to Morley 345kV substation.
ERCOT project 103797D · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
765 Dec 2031 MORLEY
Wharton County
MORLEY
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 765kV CEHE substation. Install 765/345kV Autotransformer A3 with connection to Morley 345kV substation.
ERCOT project 103797E · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
765 Dec 2031 MORLEY to HILLJE/WOLF
Wharton County
MORLEY, HILLJE, WOLF
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Install 345kV Ckt.1 Hillje to Morley. Install 345kV Ckt.2 Hillje to Morley.
ERCOT project 103797F · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
345 Dec 2031 MORLEY to HILLJE/JULIA
Wharton County
MORLEY, HILLJE, JULIA
This models CEHE's Portion of the 765 kV STEP project
Install 765kV line from CEHE's Morley substation to AEP Blu Lacy substation.
ERCOT project 103797G · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
765 Dec 2031 MORLEY to Blu Lacy
Wharton / Nueces County
MORLEY, Blu Lacy
This models CEHE's Portion of the 765 kV STEP project
Install 765kV line from CEHE's Morley substation to Oncor's Martin Lake substation.
ERCOT project 103797H · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
765 May 2032 MORLEY to Martin Lake
Wharton / Rusk County
MORLEY, Martin Lake
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 765kV CEHE substation. Install and connect (1) 300 MVAr switchable bus reactors at Morley 765kV.
ERCOT project 103797I · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
765 Dec 2031 MORLEY
Wharton County
MORLEY
Install new midpoint 765kV CEHE substation into line from Morley to Martin Lake. Install and connect (2) 300 MVAr switchable line reactors and 2-225MVAR bus reactors.
Install new midpoint 765kV CEHE substation into line from Morley to Martin Lake. Install and connect (1) 300 MVAr switchable line reactors and 2-225MVAR bus reactors.
ERCOT project 116019A
CNP
Tier 4
Planned
Future tab
765 May 2032 CEHE_NewSub to Morley
Grimes / Wharton County
Morley

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026116019AFirst listedon the Future tab
June 1, 2026103797AFirst listedon the Future tab
June 1, 2026103797BFirst listedon the Future tab
June 1, 2026103797CFirst listedon the Future tab
June 1, 2026103797DFirst listedon the Future tab
June 1, 2026103797EFirst listedon the Future tab
June 1, 2026103797FFirst listedon the Future tab
June 1, 2026103797GFirst listedon the Future tab
June 1, 2026103797HFirst listedon the Future tab
June 1, 2026103797IFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.