WOLF

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Wharton County. First named in the release with data as of February 1, 2022.

Whartoncounty as printed
345, 765kV
CNPutility
3projects listed

Also printed as: Wolf

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Wharton, TX: ERCOT queue, 42 active of 44. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 345kV CEHE substation in BAAH configuration. Loop Ckt.64E into Morley substation to create new Ckt.64 Hillje to Morley to Wolf.
ERCOT project 103797B · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
345 Dec 2031 MORLEY to HILLJE/WOLF
Wharton County
MORLEY, HILLJE, WOLF
This models CEHE's Portion of the 765 kV STEP project
Install new Morley (MLY) 765kV CEHE substation. Install 765/345kV Autotransformer A3 with connection to Morley 345kV substation.
ERCOT project 103797E · RPG 25RPG025
CNP
Tier 1
Planned
Future tab
765 Dec 2031 MORLEY to HILLJE/WOLF
Wharton County
MORLEY, HILLJE, WOLF
This models the new CEHE Raider Substation and upgrades required for a proposed load addition
Loop 345 kV Ckt. 64 Wolf-Hillje line into the new 345 kV CEHE Raider substation. Upgrade line relaying on Ckt 64 WOLF-Raider-Hillje.
ERCOT project 110068B
CNP
Tier 4
Planned
Future tab
345 May 2029 Raider to Wolf/Hillje
Wharton County
Raider, Wolf, Hillje

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110068BStatus as reportedConceptual → Planned
October 1, 2026110068BProjected in-service dateOct 2028 → May 2029
July 13, 2026110068BFirst listedon the Future tab
June 1, 2026103797BFirst listedon the Future tab
June 1, 2026103797EFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first