22 substation names the workbook places in Webb County.
| Substation | Projects | Utilities | kV | HIFLD record |
|---|---|---|---|---|
| Avanzada | 1 | ETT | 345 | None |
| Barrera | 1 | AEP TCC | 138 | None |
| Cenizo | 1 | AEP TCC/ETT | 345 | Name and county agree |
| Chalice | 1 | ETT | 345 | None |
| Del Mar | 1 | AEP TCC | 138 | None |
| Donatello | 1 | AEP TCC | 345 | None |
| Eastpoint | 1 | AEP TCC | 138 | None |
| Fincas | 1 | AEP TCC | 138 | None |
| Laredo | 2 | AEP TCC | 138 | None |
| Laredo VFT North | 1 | ETT | 138 | None |
| Las Cruces | 1 | AEP TCC/ETT | 138 | None |
| Lobo | 3 | AEP, AEP TCC, ETT, ETT/AEP TCC/ETT | 69, 138, 345 | Name and county agree |
| Magana Hein | 1 | AEP TCC | 138 | None |
| Milo | 1 | AEP TCC/ETT | 138 | None |
| Molina | 1 | AEP TCC | 138 | None |
| North Laredo | 2 | AEP TCC | 138, 345 | None |
| Palafox | 1 | AEP TCC | 138 | None |
| Reveille | 1 | AEP TCC | 138 | None |
| Rio Bravo | 1 | AEP TCC | 138 | None |
| Triada | 1 | ETT/AEP TCC/ETT | 345 | None |
| University | 1 | AEP TCC | 138 | None |
| Wormser Road | 1 | AEP TCC | 138 | None |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.