Lobo
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Webb County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: LOBO (WEBB County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Webb, TX: ERCOT queue, 20 active of 22. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Lobo: Line settings Interconnect Guajillo to the Lobo 345 kV station ERCOT project 68252 |
ETT Tier 4 |
Under Construction Completed tab |
345 | Jan 2026 actual 2025-04 |
Lobo Webb County |
Lobo |
| Lobo: 138 kV Breaker Replacement Replace 138 kV breakers at the Lobo 138 kV station ERCOT project 76196 · utility no. TP2023015 |
AEP TCC Tier 4 |
Planned Future tab |
138 | May 2028 | Lobo Webb County |
Lobo |
| Lobo: Construct New 345 kV Terminal Interconnect Cuchillas Solar to the Lobo 345 kV station ERCOT project 76237 · utility no. TP2023320 |
ETT/AEP TCC/ETT Tier 4 |
Planned Future tab |
345 | Dec 2027 actual 2025-06 |
Lobo Webb County |
Lobo |
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Lobo to Freer: Rebuild 69 kV line Rebuild Lobo to Freer 69 kV line with 795 ACSS ERCOT project 3901 · utility no. 2596 · RTP 2013-R90 |
AEP Tier 3 |
Planned Cancelled tab |
69 | Jan 2025 | Lobo to Freer Webb / Duval County |
Lobo, Freer |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 76196 | Projected in-service date | May 2027 → May 2028 |
| July 13, 2026 | 68252 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 68252 | Projected in-service date | Jun 2025 → Jan 2026 |
| February 1, 2026 | 76196 | Projected in-service date | Dec 2026 → May 2027 |
| October 1, 2025 | 68252 | Projected in-service date | Jan 2025 → Jun 2025 |
| October 1, 2025 | 76196 | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2025 | 68252 | Moved between tabs | Completed → Current-year planned |
| February 1, 2025 | 3901 | Projected in-service date | Jun 2024 → Jan 2025 |
| February 1, 2025 | 68252 | Moved between tabs | Future → Completed |
| February 1, 2025 | 76196 | Projected in-service date | Dec 2025 → May 2026 |
| October 1, 2024 | 3901 | First listed | on the Cancelled tab |
| June 1, 2024 | 68252 | Status as reported | Planned → Under Construction |
| June 1, 2024 | 76237 | Status as reported | Conceptual → Planned |
| June 1, 2024 | 76237 | Projected in-service date | May 2025 → Dec 2027 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.