Lobo

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Webb County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.

Webbcounty as printed
69, 138, 345kV
AEP, AEP TCC, ETT, ETT/AEP TCC/ETTutility
3projects listed

A HIFLD substation record has the same name and county: LOBO (WEBB County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Webb, TX: ERCOT queue, 20 active of 22. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Lobo: Line settings
Interconnect Guajillo to the Lobo 345 kV station
ERCOT project 68252
ETT
Tier 4
Under Construction
Completed tab
345 Jan 2026
actual 2025-04
Lobo
Webb County
Lobo
Lobo: 138 kV Breaker Replacement
Replace 138 kV breakers at the Lobo 138 kV station
ERCOT project 76196 · utility no. TP2023015
AEP TCC
Tier 4
Planned
Future tab
138 May 2028 Lobo
Webb County
Lobo
Lobo: Construct New 345 kV Terminal
Interconnect Cuchillas Solar to the Lobo 345 kV station
ERCOT project 76237 · utility no. TP2023320
ETT/AEP TCC/ETT
Tier 4
Planned
Future tab
345 Dec 2027
actual 2025-06
Lobo
Webb County
Lobo

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Lobo to Freer: Rebuild 69 kV line
Rebuild Lobo to Freer 69 kV line with 795 ACSS
ERCOT project 3901 · utility no. 2596 · RTP 2013-R90
AEP
Tier 3
Planned
Cancelled tab
69 Jan 2025 Lobo to Freer
Webb / Duval County
Lobo, Freer

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202676196Projected in-service dateMay 2027 → May 2028
July 13, 202668252Moved between tabsCurrent-year planned → Completed
February 1, 202668252Projected in-service dateJun 2025 → Jan 2026
February 1, 202676196Projected in-service dateDec 2026 → May 2027
October 1, 202568252Projected in-service dateJan 2025 → Jun 2025
October 1, 202576196Projected in-service dateMay 2026 → Dec 2026
June 1, 202568252Moved between tabsCompleted → Current-year planned
February 1, 20253901Projected in-service dateJun 2024 → Jan 2025
February 1, 202568252Moved between tabsFuture → Completed
February 1, 202576196Projected in-service dateDec 2025 → May 2026
October 1, 20243901First listedon the Cancelled tab
June 1, 202468252Status as reportedPlanned → Under Construction
June 1, 202476237Status as reportedConceptual → Planned
June 1, 202476237Projected in-service dateMay 2025 → Dec 2027

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.