Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Webb County. First named in the release with data as of October 1, 2023.

Webbcounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Webb, TX: ERCOT queue, 20 active of 22. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Magana Hein: Build new 138 kV distribution station
Construct new distribution station on the Molina to Wormser Road 138 kV line
ERCOT project 73065
AEP TCC
Tier 4
Planned
Future tab
138 Dec 2027 Magana Hein
Webb County
Magana Hein

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202573065Projected in-service dateDec 2025 → Dec 2027
June 1, 202473065Projected in-service dateNov 2024 → Dec 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.