Triada
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Webb County. First named in the release with data as of May 12, 2023.
Described as new. The quoted wording calls this substation new. “Triada: Build New 345 kV Station” — project 70800 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Webb, TX: ERCOT queue, 20 active of 22. Same county, not the same substation.
Location
Webb County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, project(s) 70800 (release 2026-10-01). Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Triada: Build New 345 kV Station Interconnect Siete Wind to the new Triada 345 kV station on the Avanzada to Lobo 345 kV line ERCOT project 70800 · utility no. TP2022749 |
ETT/AEP TCC/ETT Tier 4 |
Planned Future tab |
345 | May 2027 | Triada Webb County |
Triada |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 70800 | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 70800 | Projected in-service date | Dec 2026 → May 2027 |
| February 1, 2026 | 70800 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 70800 | Projected in-service date | Nov 2026 → Dec 2026 |
| June 1, 2025 | 70800 | Projected in-service date | Jun 2026 → Nov 2026 |
| February 1, 2025 | 70800 | Projected in-service date | Nov 2027 → Jun 2026 |
| October 1, 2024 | 70800 | Projected in-service date | Jul 2026 → Nov 2027 |
| June 1, 2024 | 70800 | Projected in-service date | Oct 2024 → Jul 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.