Substation Scout

University

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Webb County. First named in the release with data as of October 1, 2020.

Webbcounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Webb, TX: ERCOT queue, 20 active of 22. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Laredo to University: Rebuild 138 kV Line
Reconductor the Del Mar to University 138 kV line
ERCOT project 57906 · utility no. 3838
AEP TCC
Tier 4
Under Construction
Current-year planned tab
138 Oct 2026 Laredo to University
Webb County
Laredo, University

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202657906Projected in-service dateJan 2026 → Oct 2026
February 1, 202657906Projected in-service dateDec 2025 → Jan 2026
October 1, 202557906Status as reportedPlanned → Under Construction
June 1, 202557906Moved between tabsFuture → Current-year planned
October 1, 202457906Projected in-service dateNov 2024 → Dec 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.