Sand Lake

Named in 8 listed projects in ERCOT’s transmission project tracking workbook, in Ward County. First named in the release with data as of June 1, 2018.

Wardcounty as printed
345, 765kV
LCRATSC, ONCOR, ONCOR/LCRA TSCutility
8projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Ward, TX: ERCOT queue, 12 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Sand Lake - Big Hill (LCRA) 765 kV Line
Add Permian Basin Reliability Plan Upgrade ID 765_Import_2E. Add a new Big Hill – Sand Lake 765-kV single-circuit line
ERCOT project 100597 · utility no. PB_765_Import2_E
ONCOR/LCRA TSC
Tier 1
Planned
Future tab
765 Dec 2030 Sand Lake to Big Hill
Ward / Schleicher County
Sand Lake, Big Hill
SandLake - North McCamey Transmission Line Addition
LCRA TSC and ONCOR joint project to add the Sand Lake-North McCamey 345-kV double-circuit transmission line. 22RPG010. Also see PMCR 69709, LCRATSC_Bearkat_NorthMcCamey_TransmissionLineAddition.
ERCOT project 102815 · RPG 22RPG010 · RTP 2021-FW15
LCRATSC
Tier 1
Under Construction
Current-year planned tab
345 Jun 2026 North McCamey to Sand Lake
Glasscock / Ward County
North McCamey, Sand Lake
Drill Hole - Sand Lake 765 kV Line
Add a new Drill Hole - Sand Lake 765 kV Line
ERCOT project 103782 · utility no. R8892 · RPG 25RPG022
ONCOR
Tier 1
Planned
Future tab
765 May 2030 Drill Hole to Sand Lake
Culberson / Ward County
Drill Hole, Sand Lake
Bearkat - North McCamey Transmission Line Addition
LCRA TSC and WETT joint project to add the Bearkat-North McCamey 345-kV double-circuit transmission line. 22RPG010
ERCOT project 69709 · RPG 22RPG010 · RTP 2021-FW15
LCRATSC
Tier 1
Under Construction
Current-year planned tab
345 Jun 2026 Bearkat to Sand Lake
Glasscock / Ward County
Bearkat, Sand Lake
Hays Hill (fka Rock Draw) 345 kV Switch
Adding Oncor's portion of TNMP Silverleaf and Cowpen 345/138-kV Stations Project (23RPG013)
ERCOT project 78044 · utility no. R8716 · RPG 23RPG013
ONCOR
Tier 1
Planned
Future tab
345 Dec 2027 Sand Lake to North McCamey
Ward / Upton County
Sand Lake, North McCamey
Blue Goose (fka Toyah Creek) 345 kV Switch
Adding Oncor's portion of TNMP Silverleaf and Cowpen 345/138-kV Stations Project (23RPG013)
ERCOT project 78046 · utility no. R8715 · RPG 23RPG013
ONCOR
Tier 1
Planned
Future tab
345 May 2027 Sand Lake to Solstice
Ward / Pecos County
Sand Lake, Solstice
Sand Lake 765/345 kV Autotransformer #1
Add Permian Basin Reliability Plan Upgrade ID 765_Import_2C. Establish the Sand Lake 765/345 kV Switch with one 765/345 kV autotransformer
ERCOT project 99241 · utility no. PB_765_Import2_C
ONCOR
Tier 1
Planned
Future tab
765 Dec 2030 Sand Lake to Sand Lake
Ward County
Sand Lake
Sand Lake 765/345 kV Autotransformer #2
Add Permian Basin Reliability Plan Upgrade ID 765_Import_2C. Add a second 765/345 kV autotransformer at Sand Lake
ERCOT project 99263 · utility no. PB_765_Import2_C
ONCOR
Tier 1
Planned
Future tab
765 Dec 2030 Sand Lake to Sand Lake
Ward County
Sand Lake

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202678044Projected in-service dateMay 2027 → Dec 2027
October 1, 202678046Projected in-service dateDec 2027 → May 2027
June 1, 2026102815Status as reportedPlanned → Under Construction
June 1, 2026103782First listedon the Future tab
June 1, 202669709Status as reportedPlanned → Under Construction
June 1, 202678046Projected in-service dateMay 2027 → Dec 2027
February 1, 2026102815First listedon the Current-year planned tab
February 1, 202669709Moved between tabsFuture → Current-year planned
February 1, 202678044Projected in-service dateDec 2026 → May 2027
February 1, 202678046Projected in-service dateDec 2026 → May 2027
October 1, 2025100597First listedon the Future tab
October 1, 202599241First listedon the Future tab
October 1, 202599263First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.