Kingfisher
Named in 6 listed projects in ERCOT’s transmission project tracking workbook, in Cameron County. First named in the release with data as of October 1, 2021.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expansion of Sharyland's Kingfisher 765 kV Station” — project 110838, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Ad Hoc TPIT: Arrow Load Serving Station Construct a new 345 kV load serving station by tapping the existing Kingfisher to North Edinburg/Stewart Road Circuits ERCOT project 110832 |
SLU Tier 4 |
Conceptual Future tab |
345 | Sep 2028 | Kingfisher to Stewart Road Cameron County |
Kingfisher, Stewart Road |
| Ad-Hoc TPIT: Arrow - System Upgrades System upgrades to accommodate the full load at Sharyland's Arrow Load Serving station. Includes 345 kV line upgrades for Mantle - Bonilla ERCOT project 110834 |
SLU Tier 1 |
Conceptual Future tab |
345 | May 2031 | Kingfisher to Frontera Cameron / Hidalgo County |
Kingfisher, Frontera |
| Ad-Hoc TPIT: Five Point Load Energization Energization of a new load seeking interconnection at Sharyland's Kingfisher Station ERCOT project 110836 |
SLU Tier 4 |
Conceptual Future tab |
345 | May 2031 | Kingfisher Cameron County |
Kingfisher |
| Ad Hoc TPIT: Expansion of Sharyland's Kingfisher 765 kV Station Expansion of Sharyland's Kingfisher Station to accommodate 765 kV voltage levels and ties. Proposed alternative is in line with ERCOT's 2024 RTP STEP Plan ERCOT project 110838 · RPG 26RPG009 |
SLU Tier 1 |
Conceptual Future tab |
765 | Dec 2031 | Kingfisher to Blu Lacy Cameron / Nueces County |
Kingfisher, Blu Lacy |
| La Palma Expansion Construct 3 Breaker Ring Bus. Construct 345 kV Line from La Palma 345 kV station to Kingfisher 345 kV (Sharyland) station. ERCOT project 64858 · utility no. TP2021588 · RPG 21RPG017 |
AEP TCC/SLU Tier 1 |
Planned Current-year planned tab |
345 | Nov 2026 | La Palma to Kingfisher Cameron County |
La Palma, Kingfisher |
| Chalybe to Kingfisher: Construct New 345 kV Double Circuit Line Construct a new 345 kV double circuit line from Chalybe to Kingfisher ERCOT project 98620 · utility no. TP2025010 · RPG 24RPG008 |
AEP TCC/AEP TCC/SLU Tier 1 |
Planned Future tab |
345 | Oct 2028 | Chalybe to Kingfisher Cameron County |
Chalybe, Kingfisher |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 110832 | First listed | on the Future tab |
| July 13, 2026 | 110834 | First listed | on the Future tab |
| July 13, 2026 | 110836 | First listed | on the Future tab |
| July 13, 2026 | 110838 | First listed | on the Future tab |
| June 1, 2026 | 64858 | Projected in-service date | Jun 2026 → Nov 2026 |
| June 1, 2026 | 98620 | Projected in-service date | Mar 2028 → Oct 2028 |
| February 1, 2026 | 64858 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 64858 | Projected in-service date | Apr 2026 → Jun 2026 |
| October 1, 2025 | 98620 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.