Named in 6 listed projects in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of February 1, 2023.

Brazoriacounty as printed
345kV
CNPutility
6projects listed

Described as new. The quoted wording calls this substation new. “New 345kV Seabreeze (SEB) substation” — project 72037A description, as the utility reported it

Reported complete. Project 72037A is on the Completed tab (actual in-service 2025-05); Project 72037B is on the Completed tab (actual in-service 2025-05), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Location

Brazoria County, TX

On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: Already in service: TPIT 72037A/B are on the Completed tab, In-Service, ISD 2025-05. Not tagged in OSM (no substation of that name, and no unnamed yard on the Dow - Oasis line could be tied to it).

Sources: ERCOT TPIT, projects 72037A, 72037B, 109613, 110063, 75830A, 78468A (release 39, 2026-10-01) · OpenStreetMap: Dow and Oasis substations; 345 kV lines in Brazoria County (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install generation for Pinewood Solar (25INR0170) at Seabreeze 345kV CEHE substation. Connect at the same generator lead as Tanglewood Solar.
ERCOT project 109613
CNP
Tier 4
Planned
Current-year planned tab
345 Oct 2026 Seabreeze to TANGLE
Brazoria County
Seabreeze, TANGLE
This models upgrades required for a proposed load addition.
Connect customer load at Seabreeze or TANGLEWOOD substations
ERCOT project 110063
CNP
Tier 4
Conceptual
Future tab
345 Dec 2027 Seabreeze to Seabreeze
Brazoria County
Seabreeze
Seabreeze 345kV Substation for Tanglewood Solar (23INR0054)
New 345kV Seabreeze (SEB) substation for generator interconnection to Tanglewood Solar (23INR0054). Loop Ckt.27B into Seabreeze substation to create new Ckt.27 DOW to Seabreeze to Oasis.
ERCOT project 72037A
CNP
Tier 4
In-Service
Completed tab
345 May 2025
actual 2025-05
Seabreeze to DOW/Oasis
Brazoria County
Seabreeze, DOW, Oasis
Seabreeze 345kV Substation for Tanglewood Solar (23INR0054)
Install generator lead from Seabreeze (SEB) substation to TANGLE (TNG) customer substation (23INR0054).
ERCOT project 72037B
CNP
Tier 4
In-Service
Completed tab
345 May 2025
actual 2025-05
Seabreeze to TANGLE
Brazoria County
Seabreeze, TANGLE
New 345kV Savannah (SAV) substation for generator interconnection to Cascade Solar (23INR0091).
New 345kV Savannah (SAV) substation for generator interconnection to Cascade Solar (23INR0091). Loop Ckt.27 into Savannah substation to create new Ckt.27 Seabreeze to Savannah to Oasis.
ERCOT project 75830A
CNP
Tier 4
Planned
Future tab
345 May 2028 Savannah to Seabreeze/Oasis
Brazoria County
Savannah, Seabreeze, Oasis
Pradera (PRD) CEHE-Owned 345kV Substation for Austin Bayou Solar (25INR0102)
New 345kV Pradera (PRD) substation for generator interconnection to Austin Bayou Solar (25INR0102). Loop Ckt.27 into Pradera substation to create new Ckt.27 Seabreeze to Pradera to Savannah.
ERCOT project 78468A
CNP
Tier 4
Planned
Future tab
345 Jan 2028 Pradera to Savannah/Seabreeze
Brazoria County
Pradera, Savannah, Seabreeze

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202678468AProjected in-service dateSep 2027 → Jan 2028
July 13, 2026109613Projected in-service dateSep 2026 → Oct 2026
July 13, 2026109613First listedon the Current-year planned tab
July 13, 2026110063First listedon the Future tab
July 13, 202675830AProjected in-service dateDec 2027 → May 2028
July 13, 202678468AMoved between tabsCurrent-year planned → Future
July 13, 202678468AProjected in-service dateDec 2026 → Sep 2027
June 1, 202672037AMoved between tabsCurrent-year planned → Completed
June 1, 202672037AStatus as reportedPlanned → In-Service
June 1, 202672037BMoved between tabsCurrent-year planned → Completed
June 1, 202672037BStatus as reportedPlanned → In-Service
February 1, 202675830AProjected in-service dateDec 2026 → Dec 2027
February 1, 202678468AMoved between tabsFuture → Current-year planned
October 1, 202572037AProjected in-service dateNov 2025 → May 2025
October 1, 202572037BProjected in-service dateNov 2025 → May 2025
October 1, 202575830AMoved between tabsCurrent-year planned → Future
October 1, 202575830AProjected in-service dateDec 2025 → Dec 2026
October 1, 202578468AProjected in-service dateJan 2027 → Dec 2026
June 1, 202572037AMoved between tabsFuture → Current-year planned
June 1, 202572037BMoved between tabsFuture → Current-year planned
June 1, 202575830AMoved between tabsFuture → Current-year planned
June 1, 202578468AProjected in-service dateDec 2026 → Jan 2027
February 1, 202572037AProjected in-service dateJan 2025 → Nov 2025
February 1, 202572037BProjected in-service dateJan 2025 → Nov 2025
February 1, 202578468AFirst listedon the Future tab
October 1, 202472037AProjected in-service dateMay 2025 → Jan 2025
October 1, 202472037BProjected in-service dateMay 2025 → Jan 2025
October 1, 202475830AProjected in-service dateMay 2025 → Dec 2025
June 1, 202472037AProjected in-service dateJan 2025 → May 2025
June 1, 202472037BProjected in-service dateJan 2025 → May 2025
June 1, 202475830AProjected in-service dateJun 2025 → May 2025
June 1, 202478468ANo longer listedfuture

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first