Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Brazoria County, plus 2 on its Cancelled tab. First named in the release with data as of February 1, 2015.

Brazoriacounty as printed
345kV
CNPutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Seabreeze 345kV Substation for Tanglewood Solar (23INR0054)
New 345kV Seabreeze (SEB) substation for generator interconnection to Tanglewood Solar (23INR0054). Loop Ckt.27B into Seabreeze substation to create new Ckt.27 DOW to Seabreeze to Oasis.
ERCOT project 72037A
CNP
Tier 4
In-Service
Completed tab
345 May 2025
actual 2025-05
Seabreeze to DOW/Oasis
Brazoria County
Seabreeze, DOW, Oasis
Facility Ratings Methodology Phase 2 (FRM2) Upgrades
Upgrade Ckt.18D DOW to Jones Creek to increase thermal limits as part of FRM2 upgrades.
ERCOT project 99453N
CNP
Tier 4
Planned
Future tab
345 May 2027 DOW to Jones Creek
Brazoria County
DOW, Jones Creek

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install new 345kV Speedway substation for interconnection to Cradle Solar (23INR0150). Loop Ckt.18B into Speedway substation to create new Ckt.18 Oasis to Speedway to DOW. Install generator lead from Speedway to CRADLE solar
Install new 345kV Speedway (SPD) substation for generator interconnection to CRADLE/ Cradle Solar (23INR0150). Loop Ckt.18B into Speedway substation to create new Ckt.18 Oasis to Speedway to DOW.
ERCOT project 75810A
CNP
Tier 4
Conceptual
Cancelled tab
345 Aug 2027 Speedway to DOW/Oasis
Brazoria County
Speedway, DOW, Oasis
Install new 345kV Huizache (HUI) substation for generator interconnection to High Chap Solar (25INR0068) & BESS (25INR0072)
Install new 345kV Huizache (HUI) substation for generator interconnection to High Chap Solar (25INR0068) & BESS (25INR0072). Loop Ckt.18 into Huizache substation to create new Ckt.18 Speedway to Huizache to DOW.
ERCOT project 79456A
CNP
Tier 4
Conceptual
Cancelled tab
345 Dec 2027 Huizache to Speedway/DOW
Brazoria County
Huizache, Speedway, DOW

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202675810AMoved between tabsFuture → Cancelled
October 1, 202675810AStatus as reportedPlanned → Conceptual
October 1, 202675810AProjected in-service dateMay 2027 → Aug 2027
June 1, 202672037AMoved between tabsCurrent-year planned → Completed
June 1, 202672037AStatus as reportedPlanned → In-Service
February 1, 202675810AProjected in-service dateJul 2026 → May 2027
February 1, 202679456AMoved between tabsFuture → Cancelled
February 1, 202679456AStatus as reportedPlanned → Conceptual
February 1, 202699453NProjected in-service dateOct 2029 → May 2027
October 1, 202572037AProjected in-service dateNov 2025 → May 2025
October 1, 202575810AMoved between tabsCurrent-year planned → Future
October 1, 202575810AProjected in-service dateOct 2025 → Jul 2026
October 1, 202579456AProjected in-service dateFeb 2027 → Dec 2027
October 1, 202599453NFirst listedon the Future tab
June 1, 202572037AMoved between tabsFuture → Current-year planned
June 1, 202575810AMoved between tabsFuture → Current-year planned
February 1, 202572037AProjected in-service dateJan 2025 → Nov 2025
October 1, 202472037AProjected in-service dateMay 2025 → Jan 2025
June 1, 202472037AProjected in-service dateJan 2025 → May 2025
June 1, 202479456AFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first