Oasis

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Brazoria County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2023.

Brazoriacounty as printed
345kV
CNPutility
4projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 345kV Oasis substation” — project 72053, as the utility reported it

A HIFLD substation record has the same name and county: OASIS (BRAZORIA County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Seabreeze 345kV Substation for Tanglewood Solar (23INR0054)
New 345kV Seabreeze (SEB) substation for generator interconnection to Tanglewood Solar (23INR0054). Loop Ckt.27B into Seabreeze substation to create new Ckt.27 DOW to Seabreeze to Oasis.
ERCOT project 72037A
CNP
Tier 4
In-Service
Completed tab
345 May 2025
actual 2025-05
Seabreeze to DOW/Oasis
Brazoria County
Seabreeze, DOW, Oasis
Oasis 345kV Substation Expansion for SOHO BESS (23INR0419)
Expand 345kV Oasis substation for SOHO BESS (23INR0419). Reposition existing Ckts. 18B and 27B Oasis to Dow and Ckt.99E Meadow to Oasis.
ERCOT project 72053
CNP
Tier 4
In-Service
Completed tab
345 Dec 2024
actual 2026-01
Oasis
Brazoria County
Oasis
New 345kV Savannah (SAV) substation for generator interconnection to Cascade Solar (23INR0091).
New 345kV Savannah (SAV) substation for generator interconnection to Cascade Solar (23INR0091). Loop Ckt.27 into Savannah substation to create new Ckt.27 Seabreeze to Savannah to Oasis.
ERCOT project 75830A
CNP
Tier 4
Planned
Future tab
345 May 2028 Savannah to Seabreeze/Oasis
Brazoria County
Savannah, Seabreeze, Oasis
Oasis 345kV Substation / SOHO BESS II (25INR0162)
Install SOHO BESS II at Oasis 345kV substation… Connect at the same generator lead as SOHO BESS (SOHO BESS II - 25INR0162)
ERCOT project 78455
CNP
Tier 4
Planned
Current-year planned tab
345 Dec 2026 Oasis
Brazoria County
Oasis

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install new 345kV Speedway substation for interconnection to Cradle Solar (23INR0150). Loop Ckt.18B into Speedway substation to create new Ckt.18 Oasis to Speedway to DOW. Install generator lead from Speedway to CRADLE solar
Install new 345kV Speedway (SPD) substation for generator interconnection to CRADLE/ Cradle Solar (23INR0150). Loop Ckt.18B into Speedway substation to create new Ckt.18 Oasis to Speedway to DOW.
ERCOT project 75810A
CNP
Tier 4
Conceptual
Cancelled tab
345 Aug 2027 Speedway to DOW/Oasis
Brazoria County
Speedway, DOW, Oasis

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202675810AMoved between tabsFuture → Cancelled
October 1, 202675810AStatus as reportedPlanned → Conceptual
October 1, 202675810AProjected in-service dateMay 2027 → Aug 2027
July 13, 202675830AProjected in-service dateDec 2027 → May 2028
June 1, 202672037AMoved between tabsCurrent-year planned → Completed
June 1, 202672037AStatus as reportedPlanned → In-Service
June 1, 202672053First listedon the Completed tab
February 1, 202672053No longer listedcompleted
February 1, 202675810AProjected in-service dateJul 2026 → May 2027
February 1, 202675830AProjected in-service dateDec 2026 → Dec 2027
February 1, 202678455Moved between tabsFuture → Current-year planned
February 1, 202678455Projected in-service dateFeb 2026 → Dec 2026
October 1, 202572037AProjected in-service dateNov 2025 → May 2025
October 1, 202575810AMoved between tabsCurrent-year planned → Future
October 1, 202575810AProjected in-service dateOct 2025 → Jul 2026
October 1, 202575830AMoved between tabsCurrent-year planned → Future
October 1, 202575830AProjected in-service dateDec 2025 → Dec 2026
October 1, 202578455Projected in-service dateJun 2026 → Feb 2026
June 1, 202572037AMoved between tabsFuture → Current-year planned
June 1, 202575810AMoved between tabsFuture → Current-year planned
June 1, 202575830AMoved between tabsFuture → Current-year planned
June 1, 202578455Moved between tabsCompleted → Future
June 1, 202578455Projected in-service dateJan 2025 → Jun 2026
February 1, 202572037AProjected in-service dateJan 2025 → Nov 2025
February 1, 202572053Moved between tabsFuture → Completed
February 1, 202578455Moved between tabsFuture → Completed
February 1, 202578455Projected in-service dateNov 2024 → Jan 2025
October 1, 202472037AProjected in-service dateMay 2025 → Jan 2025
October 1, 202472053Projected in-service dateNov 2024 → Dec 2024
October 1, 202475830AProjected in-service dateMay 2025 → Dec 2025
June 1, 202472037AProjected in-service dateJan 2025 → May 2025
June 1, 202475830AProjected in-service dateJun 2025 → May 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.