Substation Scout

TANGLE

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of February 1, 2023.

Brazoriacounty as printed
345kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Seabreeze 345kV Substation for Tanglewood Solar (23INR0054)
Install generator lead from Seabreeze (SEB) substation to TANGLE (TNG) customer substation (23INR0054).
ERCOT project 72037B
CNP
Tier 4
In-Service
Completed tab
345 May 2025
actual 2025-05
Seabreeze to TANGLE
Brazoria County
Seabreeze, TANGLE

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202672037BMoved between tabsCurrent-year planned → Completed
June 1, 202672037BStatus as reportedPlanned → In-Service
October 1, 202572037BProjected in-service dateNov 2025 → May 2025
June 1, 202572037BMoved between tabsFuture → Current-year planned
February 1, 202572037BProjected in-service dateJan 2025 → Nov 2025
October 1, 202472037BProjected in-service dateMay 2025 → Jan 2025
June 1, 202472037BProjected in-service dateJan 2025 → May 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →