Substation Scout

Speedway

Named in 0 listed projects in ERCOT’s transmission project tracking workbook, in Brazoria County, plus 3 on its Cancelled tab. First named in the release with data as of October 1, 2023.

Brazoriacounty as printed
345kV
CNPutility
0projects listed

Projects cancelled. Every project naming Speedway is on the Cancelled tab of ERCOT's workbook.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

No projects.

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install new 345kV Speedway substation for interconnection to Cradle Solar (23INR0150). Loop Ckt.18B into Speedway substation to create new Ckt.18 Oasis to Speedway to DOW. Install generator lead from Speedway to CRADLE solar
Install new 345kV Speedway (SPD) substation for generator interconnection to CRADLE/ Cradle Solar (23INR0150). Loop Ckt.18B into Speedway substation to create new Ckt.18 Oasis to Speedway to DOW.
ERCOT project 75810A
CNP
Tier 4
Conceptual
Cancelled tab
345 Aug 2027 Speedway to DOW/Oasis
Brazoria County
Speedway, DOW, Oasis
Install new 345kV Speedway substation for interconnection to Cradle Solar (23INR0150). Loop Ckt.18B into Speedway substation to create new Ckt.18 Oasis to Speedway to DOW. Install generator lead from Speedway to CRADLE solar
Install generator lead from Speedway (SPD) substation to CRADLE (CDL) customer substation (23INR0150).
ERCOT project 75810B
CNP
Tier 4
Conceptual
Cancelled tab
345 Aug 2027 Speedway to CRADLE
Brazoria County
Speedway, CRADLE
Install new 345kV Huizache (HUI) substation for generator interconnection to High Chap Solar (25INR0068) & BESS (25INR0072)
Install new 345kV Huizache (HUI) substation for generator interconnection to High Chap Solar (25INR0068) & BESS (25INR0072). Loop Ckt.18 into Huizache substation to create new Ckt.18 Speedway to Huizache to DOW.
ERCOT project 79456A
CNP
Tier 4
Conceptual
Cancelled tab
345 Dec 2027 Huizache to Speedway/DOW
Brazoria County
Huizache, Speedway, DOW

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202675810AMoved between tabsFuture → Cancelled
October 1, 202675810AStatus as reportedPlanned → Conceptual
October 1, 202675810AProjected in-service dateMay 2027 → Aug 2027
October 1, 202675810BMoved between tabsFuture → Cancelled
October 1, 202675810BStatus as reportedPlanned → Conceptual
October 1, 202675810BProjected in-service dateMay 2027 → Aug 2027
February 1, 202675810AProjected in-service dateJul 2026 → May 2027
February 1, 202675810BProjected in-service dateJul 2026 → May 2027
February 1, 202679456AMoved between tabsFuture → Cancelled
February 1, 202679456AStatus as reportedPlanned → Conceptual
October 1, 202575810AMoved between tabsCurrent-year planned → Future
October 1, 202575810AProjected in-service dateOct 2025 → Jul 2026
October 1, 202575810BMoved between tabsCurrent-year planned → Future
October 1, 202575810BProjected in-service dateOct 2025 → Jul 2026
October 1, 202579456AProjected in-service dateFeb 2027 → Dec 2027
June 1, 202575810AMoved between tabsFuture → Current-year planned
June 1, 202575810BMoved between tabsFuture → Current-year planned
June 1, 202479456AFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first