Reed Farm

Named in 2 PJM planning documents for 1 project, from June 5, 2025 to October 8, 2025.

Newdescribed as
DOMzone
230kVkV as printed
2mentions

Described as new: “new substation (Reed Farm)” — source, page 8

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental South Fork 230kV Delivery - NOVEC
DOM-2023-0002 · s3722
Engineering $19.0M 09/30/2026 162.0 MW 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 66
Dominion Transmission Zone: Supplemental South Fork 230kV Delivery - NOVEC “new substation (Reed Farm)”
230kV
2025-06-05 TEAC
Item 08 - DOM Supplemental Projects p. 8
Dominion Transmission Zone: Supplemental South Fork 230kV Delivery - NOVEC “new substation (Reed Farm)”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.