St. Marys

Named in 3 PJM planning documents for 1 project, from September 19, 2025 to October 6, 2026.

Existingdescribed as
DAYTONzone
69 kVkV as printed
3mentions

Also printed as: St. Marys substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton DBA AES Ohio Transmission Zone M-3 Process
Dayton-2023-003 · S3752.1 - .3
Conceptual $ 43.2 M 10/2029 ~16MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 06/2027 → 10/2029 2025-09-19 2026-10-06
Substations named BOTKINS; ST MARYS → AMSTERDAM; BOTKINS; JACKSON CENTER; NEW KNOXVILLE DELIVERY POINT; ST MARYS 2026-10-06 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dayton Local Plan Submission of the supplemental projects for 2026 p. 7
Dayton DBA AES Ohio Transmission Zone M-3 Process “Install 2 new 69 kV breakers at St. Marys substation”
69 kV
2026-09-30* SRRTEP Western
Datyon local plan submission of the supplemental projects for 2026 RTEP p. 7
Dayton DBA AES Ohio Transmission Zone M-3 Process “Install 2 new 69 kV breakers at St. Marys substation”
69 kV
2025-09-19 SRRTEP Western
Item 05 - Dayton Supplemental Projects p. 6
Dayton DBA AES Ohio Transmission Zone M-3 Process “Install 2 new 69 kV breakers at St. Marys substation to accommodate the new 69 kV line”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.