Named in 1 PJM planning document for 2 projects, on July 7, 2026.

Not stateddescribed as
PJM system-widezone
345 kV, 345kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Approved Targeted Market Efficiency Project (TMEP) b2971: Burnham – Munster 345kV (ComEd-NIPS)
b2971
Not printed $7M 6/1/2020 Not printed 2026-07-07
TEAC
Scope Change b2971.1: Burnham-Munster Sag Mitigation
b2971.1
Not printed $500,000 6/1/2020 Not printed 2026-07-07
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-07-07 TEAC
Item 15 - Reliability Analysis Update p. 7
Approved Targeted Market Efficiency Project (TMEP) b2971: Burnham – Munster 345kV (ComEd-NIPS) No role wording
345kV
2026-07-07 TEAC
Item 15 - Reliability Analysis Update p. 8
Scope Change b2971.1: Burnham-Munster Sag Mitigation No role wording
345 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.