Substation Scout

Willard

Named in 1 PJM planning document for 1 project, on October 8, 2024.

Not stateddescribed as
ATSIzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New London 69 kV Project
AEP-2019-OH034 · s2748.8
Not printed $10.0M 9/3/2025 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 3
New London 69 kV Project No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this