Substation Scout

Wauseon

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to August 4, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
3mentions

Also printed as: Wauseon Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Supplemental s2237.2 Scope Change
ATSI-2019-082 · s2237.2
Conceptual $67M 5/14/2027 Not printed 2026-08-04
TEAC
ATSI Transmission Zone M-3 Process Midway – Richland – Wauseon 138 kV Line
ATSI-2020-028 · s3370.1
Not printed $44 M 12/31/2026 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 41
ATSI Transmission Zone M-3 Process Midway – Richland – Wauseon 138 kV Line “Upgrade substation conductor at Midway Substation and Wauseon Substation.”
2026-08-04 TEAC
Item 04 - ATSI Supplemental Projects p. 8
Supplemental s2237.2 Scope Change No role wording
138 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 41
ATSI Transmission Zone M-3 Process Midway – Richland – Wauseon 138 kV Line “Upgrade substation conductor at Midway Substation and Wauseon Substation.”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.