Roberts

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
ATSIzone
138 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ATSI Transmission Zone M-3 Process Galion – Roberts North 138 kV Line and Galion – Roberts South 138 kV Line
ATSI-2024-024 · s3469.1
Not printed $66.5 M 8/27/2026 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 83
ATSI Transmission Zone M-3 Process Galion – Roberts North 138 kV Line and Galion – Roberts South 138 kV Line “Roberts  Replace substation conductor.”
138 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 83
ATSI Transmission Zone M-3 Process Galion – Roberts North 138 kV Line and Galion – Roberts South 138 kV Line “Replace substation conductor.”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.