North Washington
Named in 3 PJM planning documents for 2 projects, from September 19, 2025 to April 15, 2026.
Existingdescribed as
APSzone
138 kVkV as printed
3mentions
Also printed as: North Washington Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Kiski Valley - North Washington 138 kV Line APS-2025-027 |
Conceptual | $2.79M | 03/27/2030 | 9.9 MW | 2025-10-17 SRRTEP Western |
| North Washington (Kiski Valley) 138 kV Line APS-2026-008 |
Not printed | Not printed | Not printed | 18 MW | 2026-04-15 SRRTEP Western |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| In-service date | 6/9/2027 → 03/27/2030 | 2025-09-19 | 2025-10-17 |
| Substations named | KISKI VALLEY; NORTH WASHINGTON → KLINES MILL; MEADOW BROOK; RIVERTON | 2026-04-15 | 2026-07-17 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-04-15 | SRRTEP Western Item 02 - APS Supplemental Project p. 3 |
North Washington (Kiski Valley) 138 kV Line | No role wording 138 kV |
| 2025-10-17 | SRRTEP Western Item 02 - APS Supplemental Projects p. 14 |
Kiski Valley - North Washington 138 kV Line | “Adjust relay settings at Kiski Valley and North Washington substations” 138 kV |
| 2025-09-19 | SRRTEP Western Item 02 - APS Supplemental Projects p. 4 |
Kiski Valley - North Washington 138 kV Line | “The delivery point is adjacent to North Washington Substation” 138 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.