Damascus
Named in 2 PJM planning documents for 2 projects, on October 8, 2024.
Existingdescribed as
APSzone
230 kVkV as printed
4mentions
Also printed as: Damascus Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Damascus – Mount Airy 230 kV Misoperation Relays APS-2023-026 · s3091.1 |
Not printed | $ 2.2 M | 12/22/2023 | Not printed | 2024-10-08 TEAC |
| Damascus – Montgomery 230 kV Line Misoperation Relay Project APS-2024-001 · s3451.1 |
Not printed | $2.8M | 06/01/2027 | Not printed | 2024-10-08 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 100 |
Damascus – Montgomery 230 kV Line Misoperation Relay Project | “At Damascus Substation: Replace circuit breakers, disconnect switches, line trap, substation conductor and relaying” 230 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 25 |
Damascus – Mount Airy 230 kV Misoperation Relays | “Replace circuit switcher and limiting substation conductor at Damascus” 230 kV |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 100 |
Damascus – Montgomery 230 kV Line Misoperation Relay Project | “At Damascus Substation:” 230 kV |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 25 |
Damascus – Mount Airy 230 kV Misoperation Relays | “Replace circuit switcher and limiting substation conductor at Damascus” 230 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.