Whitewood

Named in 2 PJM planning documents for 2 projects, from March 14, 2025 to July 18, 2025.

Existingdescribed as
AEPzone
138kVkV as printed
2mentions

Also printed as: Whitewood substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline B3333 Reactivation and Scope Change
B3333
Not printed $106.589M 12/10/2027 Not printed 2025-07-18
SRRTEP Western
AEP Transmission Zone: Baseline B3333 Cancellation
B3333
Cancelled $40.171 M 6/1/2023 Not printed 2025-03-14
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$40.171 M → $106.589M 2025-07-18 2025-07-18

Every mention

DateDocumentProjectWhat the document says about it
2025-07-18 SRRTEP Western
Item 01 - Reliability Analysis Update p. 3
AEP Transmission Zone: Baseline B3333 Reactivation and Scope Change “Install 43.2 57.6 MVAR Cap bank at Whitewood along with 138kV breaker.”
138kV
2025-03-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 3
AEP Transmission Zone: Baseline B3333 Cancellation “Install 46.1 MVAR Cap bank at Whitewood substation along with a 138kV breaker.”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.