Substation Scout

Kanawha

Named in 3 PJM planning documents for 1 project, from August 15, 2025 to October 6, 2026.

Existingdescribed as
AEPzone
138 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Pax Branch, WV
AEP-2025-AP004 · s3825.1
Engineering 0 11/14/2025 7.5 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 2025 → 11/14/2025 2025-02-14 2025-08-15
Substations named BRADLEY; KANAWHA; PAX BRANCH → BRADLEY; KANAWHA; PAX BRANCH; SAND BRANCH 2025-08-15 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 15
Pax Branch, WV No role wording
138 kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 15
Pax Branch, WV No role wording
138 kV
2025-08-15 SRRTEP Western
Item 02 - AEP Supplemental Projects p. 7
Pax Branch, WV “existing Bradley - Kanawha 138 kV line”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this