Bradley
Named in 5 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.
Existingdescribed as
AEPzone
138 kV, 46 kVkV as printed
5mentions
Also printed as: Bradley Station
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Beckley , WV AEP-2022-AP015, AEP-2022-AP016, AEP-2022-AP017, AEP-2022-AP018, AEP-2022-AP019, AEP-2022-AP020, AEP-2022-AP021 · s3139.1-.35 |
Conceptual | $150.9M | 6/10/2031 | Not printed | 2024-10-08 TEAC |
| Pax Branch, WV AEP-2025-AP004 · s3825.1 |
Engineering | 0 | 11/14/2025 | 7.5 MW | 2026-10-06 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| In-service date | 2025 → 11/14/2025 | 2025-02-14 | 2025-08-15 |
| Substations named | BRADLEY; KANAWHA; PAX BRANCH → BRADLEY; KANAWHA; PAX BRANCH; SAND BRANCH | 2025-08-15 | 2026-10-06 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-07* | SRRTEP Western AEP local plan submission of the supplemental projects for 2026 RTEP p. 15 |
Pax Branch, WV | No role wording 138 kV |
| 2026-10-06 | TEAC Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 15 |
Pax Branch, WV | No role wording 138 kV |
| 2026-09-08* | SRRTEP Western AEP local plan submission of the supplemental projects for 2024 RTEP p. 65 |
Beckley , WV | “Bradley Station: Remove 46 kV CB-F” 46 kV |
| 2025-08-15 | SRRTEP Western Item 02 - AEP Supplemental Projects p. 7 |
Pax Branch, WV | “existing Bradley - Kanawha 138 kV line” 138 kV |
| 2024-10-08 | TEAC Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 65 |
Beckley , WV | “Remove 46 kV CB-F, Retire 46 kV CB-J” 46 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.