Stotesbury

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
AEPzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Beckley , WV
AEP-2022-AP015, AEP-2022-AP016, AEP-2022-AP017, AEP-2022-AP018, AEP-2022-AP019, AEP-2022-AP020, AEP-2022-AP021 · s3139.1-.35
Conceptual $150.9M 6/10/2031 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 64
Beckley , WV “Stotesbury: Replace existing hard tap with a new 3-way phase over phase switch”
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 64
Beckley , WV “Replace existing hard tap with a new 3-way phase over phase switch”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.