Weirwood-Eastville substation interconnection queue
1 active project totaling 7.6 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Weirwood-Eastville as the point of interconnection, all in Northampton County, VA.
Target commercial operation dates as filed run from Jun 2016 to Apr 2017 (2 filings).
1active projects
7.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| Z2-012 | Hecate Energy Cherrydale | 69 | 7.6 | Solar | In Service | Apr 2017 |
| X3-040 | Weirwood-Eastville 69kV | 69 | 0 | Wind | Withdrawn | Jun 2016 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Northampton County, VA
- Bayview: 1 active, 0.5 MW of 5 filed