Hecate Energy Cherrydale (Z2-012) is listed in the PJM interconnection queue as a 7.6 MW solar project in Northampton County, VA. The filing names Weirwood-Eastville as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of April 1, 2017.
| Queue ID | Z2-012 |
|---|---|
| Project name | Hecate Energy Cherrydale |
| Status (as published) | In Service |
| Substation | Weirwood-Eastville |
| Point of interconnection | Weirwood-Eastville 69kV |
| County | Northampton |
| State | VA |
| Voltage | 69 kV |
| Capacity | 7.6 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2017-04-01 |
| Source dataset | serial |
Same substation and county
Weirwood-Eastville substation: 2 requests in the PJM queue, 1 active totaling 7.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| X3-040 | Weirwood-Eastville 69kV | 0 | Wind | Withdrawn |
Northampton, VA: 11 requests in the PJM queue, 3 active totaling 17.5 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 20 |
| MW capacity | 7.6 |
| MFO | 20 |