Sullivan substation interconnection queue

6 active projects totalling 4,818 MW in the PJM queue, plus 7 with terminal status (shown greyed).

6active projects
4,818active MW
13total filed
Queue IDProjectkVMWResourceStatus
C01-1394 Sullivan 765 kV 765 2,300 Nuclear Active
C01-1395 Sullivan 765 kV 765 2,300 Nuclear Active
Y2-095 Sullivan 765 kV 765 1,211 Coal Withdrawn
AF1-088 Grain Belt Transmission 345 1,000 Not reported Withdrawn
Y2-116 Sullivan 765 kV 765 600 Coal Withdrawn
AF2-008 Grain Belt Transmission 345 500 Not reported Withdrawn
AH1-084 Sullivan 345 kV 345 500 Not reported Withdrawn
AC2-157 Trade Post Solar Energy Center 345 76 Solar Partially in Service - Under Construction
AE2-276 Trade Post Energy Storage 345 50 Battery Engineering and Procurement
AI2-160 Sullivan 345 kV 345 48 Solar Withdrawn
C01-1629 Sullivan 345 kV 345 48 Solar Active
AH1-292 Sullivan 345 kV 345 44 Solar Active
AH1-085 Sullivan 345kV 345 0 Not reported Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.