Sullivan-Rockport substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 5 with terminal status (shown grayed).
5 PJM queue filings name Sullivan-Rockport as the point of interconnection, all in Sullivan County, IN.
Target commercial operation dates as filed run from Jun 2023 to Jun 2024 (5 filings).
Transmission owner as filed: AEP (4 filings).
0active projects
0active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG1-522 | Sullivan-Rockport 765 kV | 765 | 180 | Solar | Withdrawn | Jun 2023 |
| AG1-523 | Sullivan-Rockport 765 kV | 765 | 180 | Solar | Withdrawn | Jun 2023 |
| AG1-524 | Sullivan-Rockport 765 kV | 765 | 180 | Solar | Withdrawn | Jun 2023 |
| AG1-525 | Sullivan-Rockport 765 kV | 765 | 180 | Solar | Withdrawn | Jun 2023 |
| AG2-683 | Sullivan-Rockport 765 kV | 765 | 180 | Solar | Withdrawn | Jun 2024 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Sullivan County, IN
- Sullivan: 6 active, 4,818 MW of 13 filed