Sullivan 765 kV (C01-1395) is listed in the PJM interconnection queue as a 2,300 MW nuclear project in Sullivan County, IN. The filing names Sullivan as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 1, 2034.

Queue IDC01-1395
Project nameSullivan 765 kV
Status (as published)Active
SubstationSullivan
Point of interconnectionSullivan 765 kV
CountySullivan
StateIN
Voltage765 kV
Capacity2,300 MW
Resource (as published)Nuclear
Resource categoryNuclear (normalized for filtering)
Target commercial operation2034-06-01
Source datasetcycle

Same substation and county

Sullivan substation: 13 requests in the PJM queue, 6 active totaling 4,818 MW.

Queue IDProjectMWResourceStatus
C01-1394Sullivan 765 kV2,300NuclearActive
AC2-157Trade Post Solar Energy Center76SolarPartially in Service - Under Construction
AE2-276Trade Post Energy Storage50BatteryEngineering and Procurement
C01-1629Sullivan 345 kV48SolarActive
AH1-292Sullivan 345 kV44SolarActive
Y2-095Sullivan 765 kV1,211CoalWithdrawn
AF1-088Grain Belt Transmission1,000Not reportedWithdrawn
Y2-116Sullivan 765 kV600CoalWithdrawn
AF2-008Grain Belt Transmission500Not reportedWithdrawn
AH1-084Sullivan 345 kV500Not reportedWithdrawn
AI2-160Sullivan 345 kV48SolarWithdrawn
AH1-085Sullivan 345kV0Not reportedWithdrawn

Sullivan, IN: 19 requests in the PJM queue, 8 active totaling 5,778 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperIndiana Michigan Power Company
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy2300.0
MW capacity2300.0
MFO2300.0
Submitted date4/23/2026
Last updated6/23/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.