South Hertford substation interconnection queue

1 active project totalling 7.2 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
7.2active MW
3total filed
Queue IDProjectkVMWResourceStatus
C01-1693 South Hertford 34.5 kV 34.5 7.2 Solar Active
AE2-304 South Hertford Solar 34 3.6 Solar Withdrawn
AB2-186 South Hertford 34.5kV 34.5 3.5 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.