Sorenson substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 7 with terminal status (shown grayed).
7 PJM queue filings name Sorenson as the point of interconnection, all in Huntington County, IN.
Target commercial operation dates as filed run from Dec 2024 to Dec 2028 (7 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI1-022 | Sorenson 345 kV | 345 | 450 | Battery | Withdrawn | Dec 2026 |
| AH2-414 | Sorenson 345 kV | 345 | 350 | Battery | Withdrawn | Dec 2026 |
| AH2-413 | Sorenson 345 kV | 345 | 339 | Hybrid | Withdrawn | Dec 2026 |
| AH1-548 | Sorenson 345 kV | 345 | 96 | Solar | Withdrawn | Dec 2024 |
| AH1-014 | Sorenson 345 kV | 345 | 67.1 | Solar | Withdrawn | Dec 2024 |
| AI2-425 | Sorenson 345 kV | 345 | 40 | Solar | Withdrawn | Dec 2028 |
| AI2-424 | Sorenson 345 kV | 345 | 28 | Solar | Withdrawn | Dec 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Same name on other Substation Scout pages
Other sources that print a substation named “Sorenson” in IN. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- Sorenson: Expansion Tracker, PJM planning: AEP state not printed
Other PJM queue substations in Huntington County, IN
- Huntington Jct.: none active of 2 filed
- Rock Creek: none active of 2 filed