1 active project totalling 24.1 MW in the PJM queue, plus 12 with terminal status (shown greyed).

1active projects
24.1active MW
13total filed
Queue IDProjectkVMWResourceStatus
AI1-022 Sorenson 345 kV 345 450 Battery Withdrawn
AH2-414 Sorenson 345 kV 345 350 Battery Withdrawn
AH2-413 Sorenson 345 kV 345 339 Hybrid Withdrawn
AF1-092 Bowfin Solar 138 115 Hybrid Withdrawn
AH1-291 Rock Creek-Hummel Creek 138 kV 138 111 Solar Withdrawn
AH1-548 Sorenson 345 kV 345 96 Solar Withdrawn
AH1-014 Sorenson 345 kV 345 67.1 Solar Withdrawn
AI2-150 Rock Creek 138 kV 138 44.4 Solar Withdrawn
AI2-425 Sorenson 345 kV 345 40 Solar Withdrawn
AI1-003 Rock Creek 138 kV 138 34 Wind Withdrawn
AI2-424 Sorenson 345 kV 345 28 Solar Withdrawn
AF2-094 Huntington Jct. 138 kV 138 26.4 Solar Withdrawn
AE2-234 Maple Solar 69 24.1 Solar Engineering and Procurement