Rockport substation interconnection queue

3 active projects totaling 2,240 MW in the PJM queue, plus 4 with terminal status (shown grayed).

Target commercial operation dates as filed run from Mar 2011 to Sep 2030 (7 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (3 filings).

3active projects
2,240active MW
7total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1156 Rockport 765kV 765 1,520 Gas Active Sep 2030
AG2-072 Rockport 765 kV 765 700 Hybrid Active Sep 2029
AE1-214 Rockport 765 kV 765 625 Hybrid Withdrawn Dec 2023
AF2-353 Rockport 765 kV 765 560 Hybrid Withdrawn Sep 2023
R44 Rockport 765kV 765 485 Coal Withdrawn Mar 2011
AE2-130 Rockport 765 kV 765 480 Hybrid Withdrawn Dec 2022
R97 Rockport Unit 1 765 20 Coal In Service Nov 2011

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Rockport (AEP, 2 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Spencer County, IN

All 11 PJM queue filings in Spencer County, IN.

Other PJM queue substations in Henderson County, KY

No other substation in Henderson County, KY is named as a point of interconnection in the PJM queue.

All 1 PJM queue filings in Henderson County, KY.