Substation Scout

Ravenswood-Hemlock substation interconnection queue

1 active project totalling 29 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
29active MW
2total filed
Queue IDProjectkVMWResourceStatus
AC1-082 Great Bend 69 29 Solar Partially in Service - Under Construction
AI2-313 Ravenswood-Hemlock 69kV 69 17.1 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.