Peninsula substation interconnection queue

1 active project totaling 29.1 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Peninsula as the point of interconnection, all in VA.

Target commercial operation dates as filed run from Jun 2022 to Apr 2028 (2 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: Dominion (1 filing).

1active projects
29.1active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1455 Peninsula 34.5 kV 34.5 29.1 Battery Active Apr 2028
AD2-164 Langley AFB Generation 34.5 26.7 Gas Withdrawn Jun 2022

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Hampton County, VA

No other substation in Hampton County, VA is named as a point of interconnection in the PJM queue.

All 1 PJM queue filings in Hampton County, VA.

Other PJM queue substations in City of Hampton, VA

No other substation in City of Hampton, VA is named as a point of interconnection in the PJM queue.

All 4 PJM queue filings in City of Hampton, VA.