Lanesville-Brokaw substation interconnection queue
1 active project totaling 26 MW in the PJM queue, plus 3 with terminal status (shown grayed).
4 PJM queue filings name Lanesville-Brokaw as the point of interconnection, all in Logan County, IL.
Target commercial operation dates as filed run from Dec 2024 to Dec 2025 (4 filings).
Transmission owner as filed: ComEd (1 filing).
1active projects
26active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI2-166 | Lanesville-Brokaw | n/r | 78 | Wind | Withdrawn | Dec 2025 |
| AI2-167 | Lanesville-Brokaw 345 kV | 345 | 78 | Wind | Withdrawn | Dec 2024 |
| AC1-053 | Top Hat Wind Energy Center | n/r | 26 | Wind | In Service | Dec 2025 |
| AG1-236 | Ramble Wind | 345 | 23.4 | Wind | Withdrawn | Dec 2024 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Logan County, IL
- Brokaw-Lanesville: 5 active, 52.8 MW of 6 filed