Ebersole #2-Fostoria Central substation interconnection queue
1 active project totaling 81.8 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Ebersole #2-Fostoria Central as the point of interconnection, all in Hancock County, OH.
Target commercial operation dates as filed run from Dec 2025 to Dec 2026 (2 filings). 1 active filing targets a date after November 27, 2026.
1active projects
81.8active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE1-146 | Border Basin | 138 | 81.8 | Solar | Partially in Service - Under Construction | Dec 2026 |
| AI2-305 | Ebersole #2-Fostoria Central 138 kV | 138 | 33.6 | Solar | Withdrawn | Dec 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Tracked changes at this substation
1 change to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-09-28 | AE1-146 | Status change | n/a | Under Construction → Partially in Service - Under Construction |
Other PJM queue substations in Hancock County, OH
- Fostoria Central: none active of 5 filed
- East Lima-Fostoria Central: none active of 2 filed