Dauphin-Pine Grove substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
3 PJM queue filings name Dauphin-Pine Grove as the point of interconnection, all in Dauphin County, PA.
Target commercial operation dates as filed run from Mar 2020 to Mar 2022 (3 filings).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE2-293 | Dauphin-Pine Grove 69kV | 69 | 20 | Solar | Withdrawn | Jun 2020 |
| AE2-294 | Dauphin-Pine Grove 69 kV | 69 | 20 | Battery | Withdrawn | Mar 2020 |
| AG1-396 | Dauphin-Pine Grove 69 kV | 69 | 4 | Solar | Withdrawn | Mar 2022 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Dauphin County, PA
- Three Mile Island: 1 active, 803 MW of 2 filed
- Edgemoor: 7 active, 53.2 MW of 11 filed
- TMI: none active of 7 filed
- Dauphin: none active of 2 filed
- Hummelstown: none active of 2 filed