Crown-New Lebanon substation interconnection queue
1 active project totaling 29.9 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Crown-New Lebanon as the point of interconnection, all in Montgomery County, OH.
Target commercial operation dates as filed run from Dec 2025 to Jan 2028 (2 filings). 1 active filing targets a date after November 27, 2026.
1active projects
29.9active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF2-298 | Gem City Solar | 69 | 29.9 | Solar | Engineering and Procurement | Jan 2028 |
| AI2-303 | Crown-New Lebanon 69 kV | 69 | 18.1 | Solar | Withdrawn | Dec 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.