Chestnut substation interconnection queue

2 active projects totalling 347.7 MW in the PJM queue, plus 1 with terminal status (shown greyed).

2active projects
347.7active MW
3total filed
Queue IDProjectkVMWResourceStatus
C01-2046 Chestnut 345 kV 345 320 Battery Active
AD2-159 Chestnut 345kV 345 33 Wind Withdrawn
AH1-541 Chestnut 345 kV 345 27.7 Hybrid Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.