Blue Mound-Latham substation interconnection queue

1 active project totalling 39.8 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
39.8active MW
2total filed
Queue IDProjectkVMWResourceStatus
W4-005 Radford's Run Wind Farm n/r 39.8 Wind In Service
AA1-086 Blue Mound-Latham n/r 26 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.