Double Tollgate Solar Project
PJM queue ID Z2-030
Double Tollgate Solar Project (Z2-030) is listed in the PJM interconnection queue as a 3.8 MW solar project in Clarke County, VA. The filing names Double Toll Gate as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2016.
| Queue ID | Z2-030 |
|---|---|
| Project name | Double Tollgate Solar Project |
| Status (as published) | In Service |
| Substation | Double Toll Gate |
| Point of interconnection | Double Toll Gate 34.5kV |
| County | Clarke |
| State | VA |
| Voltage | 34.5 kV |
| Capacity | 3.8 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2016-12-31 |
| Source dataset | serial |
Same substation and county
Double Toll Gate substation: 4 requests in the PJM queue, 1 active totaling 3.8 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AG2-510 | Double Toll Gate 138 kV | 60 | Solar | Withdrawn |
| AC2-135 | Double Toll Gate 34.5kV | 9.6 | Solar | Withdrawn |
| V4-053 | Double Toll Gate 138kV | 7.6 | Solar | Withdrawn |
Clarke, VA: 11 requests in the PJM queue, 2 active totaling 28.8 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 10 |
| MW capacity | 3.8 |
| MFO | 10 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.