Liberty Electric
PJM queue ID Y2-064
Liberty Electric (Y2-064) is listed in the PJM interconnection queue as a 19 MW gas project in Delaware County, PA. The filing names Printz as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 30, 2014.
| Queue ID | Y2-064 |
|---|---|
| Project name | Liberty Electric |
| Status (as published) | In Service |
| Substation | Printz |
| Point of interconnection | Printz |
| County | Delaware |
| State | PA |
| Voltage | Not reported |
| Capacity | 19 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2014-09-30 |
| Source dataset | serial |
Same substation and county
Printz substation: 7 requests in the PJM queue, 3 active totaling 74 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AA2-140 | Liberty Electric | 35 | Gas | In Service |
| T129 | Liberty | 20 | Gas | In Service |
| Y3-098 | Printz | 735 | Gas | Withdrawn |
| U3-023 | Printz 230kV | 720 | Gas | Withdrawn |
| AC1-184 | Printz | 35 | Gas | Withdrawn |
| AF2-038 | Printz 230 kV | 8 | Battery | Withdrawn |
Delaware, PA: 27 requests in the PJM queue, 12 active totaling 934.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 65.5 |
| MW capacity | 19 |
| MFO | 606.5 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.