St. Charles Combined Cycle Facility
PJM queue ID X4-006
St. Charles Combined Cycle Facility (X4-006) is listed in the PJM interconnection queue as a gas request filed at 0 MW (a net change or energy-only filing) in Charles County, MD. The filing names Kelson Ridge as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of November 1, 2016.
| Queue ID | X4-006 |
|---|---|
| Project name | St. Charles Combined Cycle Facility |
| Status (as published) | In Service |
| Substation | Kelson Ridge |
| Point of interconnection | Kelson Ridge 230kV |
| County | Charles |
| State | MD |
| Voltage | 230 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2016-11-01 |
| Source dataset | serial |
Same substation and county
Kelson Ridge substation: 4 requests in the PJM queue, 2 active totaling 75 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AD1-114 | CPV Maryland | 75 | Gas | In Service |
| W4-044 | Kelson Ridge 230kV | 725 | Gas | Withdrawn |
| X4-007 | Kelson Ridge 230kV | 0 | Gas | Withdrawn |
Charles, MD: 50 requests in the PJM queue, 12 active totaling 1,900.5 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 60 |
| MW capacity | 0 |
| MFO | 785 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.