PJM queue ID V4-054

NJ Oak Solar (V4-054) is listed in the PJM interconnection queue as a 3.8 MW solar project in Cumberland County, NJ. The filing names Fairfield Township as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 20, 2011.

Queue IDV4-054
Project nameNJ Oak Solar
Status (as published)In Service
SubstationFairfield Township
Point of interconnectionFairfield Township 12kV
CountyCumberland
StateNJ
Voltage12 kV
Capacity3.8 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2011-12-20
Source datasetserial

Same substation and county

Fairfield Township substation: 2 requests in the PJM queue, 1 active totaling 3.8 MW.

Queue IDProjectMWResourceStatus
W1-097Fairfield Township 12kV0SolarWithdrawn

Cumberland, NJ: 94 requests in the PJM queue, 15 active totaling 1,148.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy10
MW capacity3.8
MFO10

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first