Substation Scout

Westwood Generation

PJM queue ID U2-067

Westwood Generation (U2-067) is listed in the PJM interconnection queue as a 2.5 MW coal project in Bucks County, PA. The filing names Eldred-Pine Grove as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of July 1, 2008.

Queue IDU2-067
Project nameWestwood Generation
Status (as published)In Service
SubstationEldred-Pine Grove
Point of interconnectionEldred-Pine Grove 69kV
CountyBucks
StatePA
Voltage69 kV
Capacity2.5 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Target commercial operation2008-07-01
Source datasetserial

Same substation and county

Eldred-Pine Grove substation: 2 requests in the PJM queue, 2 active totaling 4.3 MW.

Queue IDProjectMWResourceStatus
Y3-034Stonegate Renewable Energy1.8GasIn Service

Bucks, PA: 19 requests in the PJM queue, 9 active totaling 1,363.3 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy2.5
MW capacity2.5
MFO32.5

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.